It had rained the night before.  Our first task was to cut up some of the OSB and make walkways.

The extra mud on Amy's shoes added about 5 lbs.  It stuck to everything and was impossible to get off.


Some pre-planning and building had taken place.  The slab was poured and marked for walls.  The window and door header/jack/stud/jams had been pre-build.  Now just nail it all together.   I think Amy and Lisle were really doing some powerful ministry by the number of nails that they drove.

It was a great first day.